Where will it take place?
The current level crossing is to be replaced by an underpass beneath the railway line. All traffic – including pedestrians and cyclists – will then no longer cross the tracks at ground level, but will pass underneath them.
Why is this necessary?
Apeldoorn is growing. That is why the council is working on measures to improve the city’s accessibility and traffic flow on the outer ring road. Level crossings can cause delays and represent a vulnerable point in the transport network. Laan van Erica is a key link in Apeldoorn’s outer ring road. Constructing a railway tunnel will improve traffic flow, accessibility and road safety on this section of the outer ring road. This will, in turn, contribute to better accessibility throughout Apeldoorn.
What does this mean for the local area?
A railway underpass helps to improve traffic flow, as road users no longer have to wait at a closed level crossing. Furthermore, separating rail and road traffic improves road safety for all road users.
As the project is still at the research stage, not all the implications are yet known. However, based on the initial studies, we can identify a number of areas for consideration.
Water and subsoil
Groundwater levels in the area are relatively high. We are therefore investigating how the groundwater and the existing watercourses affect the design of the tunnel. The findings of these investigations may lead to changes to the design.
Homes and businesses
We are currently investigating how much space is required to build a tunnel and what impact this will have on the neighbouring residential area of De Maten, access to De Voorwaarts, access to the Zonnehoeve neighbourhood and Apeldoorn de Maten station.
Green
There are trees and other green spaces along Laan van Erica. The construction of a tunnel also requires space above ground. As a result, some trees or green spaces may have to be removed. In the next phase, we will carry out a detailed survey and assess how and where compensation can be provided.
Where are we at now?
We are currently investigating how the tunnel can be built, how much space will be required and what the implications will be for the surrounding area. To this end, we are carrying out, amongst other things, soil investigations, groundwater studies and various design studies. No final decisions regarding the design are being made at this stage. The investigations we are carrying out will help us in our further decision-making.
Participation in this project
As a railway underpass has an impact on the immediate neighbourhood, we believe it is important to involve residents, business owners and other stakeholders. Once the studies have been completed, we will therefore engage in dialogue with the local community.
Planning
At present (autumn 2026), we are still in the research phase. In 2027, we will begin work on various studies. We will then draw up a schedule, which we will share on this webpage.
Documents
As soon as we have any plans, outlines or reports from consultation meetings, we will share them on the project page.