Woudhuis–Osseveld high-voltage transmission line

TenneT has assessed the best location for the underground cables. Three options were examined. A preferred route has emerged from these. The council proposal is currently being drawn up. This proposal will be submitted to the Mayor and Aldermen for a decision, and they will also have to decide on making the necessary budget available. We expect a decision on this to be taken in the third quarter of 2026. TenneT can then begin work on drawing up a basic design.

Phase 2: Basic design – takes approximately 24 months

Tennet werkt de voorkeurslocatie verder uit en onderzoeksbureaus doen extra onderzoek. Hierna weten we precies waar de kabels onder de grond moeten komen te liggen. Daarna kunnen we door naar de volgende fase. Als een collegebesluit wordt genomen in 2026, is het de verwachting dat TenneT op zijn vroegst pas in 2028 kan beginnen aan uitvoeren van het basisontwerp.

Phase 3: Detailed design and preparation – takes approximately 12 months

TenneT is working on the route in further detail. The design will then be detailed enough to reach agreements with landowners and users. We will also be able to amend zoning plans or environmental plans, apply for permits and make the necessary preparations.

Phase 4: Construction and completion – takes approximately 24 months

We then look for contractors and suppliers to carry out the work. Once we’ve done that, the work really gets underway: the cables are laid underground by digging or drilling. Once the cables have been installed, they are connected to the feed-in point(s) or a substation. If everything is working properly, the underground connection can be used. We then remove the old high-voltage pylons.

Videos of the cabling process

In 2013/2014, a similar project took place in Apeldoorn Zuid. You can see from the videos what is likely to happen in De Maten. These videos do not provide an exact picture, as the circumstances surrounding these projects are not always the same. The approach is similar, but the technical details may differ. For example, there is more space to work in an open area, and different machinery can be used there than in an urban area.

Uncertain planning

There are many changes taking place in the energy sector. Grid operators are under considerable pressure to resolve the issue of grid congestion. This could cause delays to the project. Furthermore, TenneT cannot carry out all projects at the same time, and there is a severe shortage of technicians. The number of staff available to carry out the work is also limited. For this reason, we cannot yet say exactly when the work will begin.

Stay up to date

We keep local residents, businesses and other stakeholders informed of any developments.