1e Wormenseweg, Apeldoorn
Home | Urban planning and development | Southwest | Improvements to 1e Wormenseweg

Improvements to 1e Wormenseweg

Apeldoorn City Council is working on improvements to the 1e Wormenseweg. The road is in poor condition and the tarmac needs replacing. At the same time, we aim to improve road safety, add more green spaces and make the public space future-proof. The project area runs from Laan van de Mensenrechten to the junction with Ruys de Beerenbrouckstraat.

Residents’ Evening, 5 October 2026

On 5 October 2026, we presented the preliminary design for the redevelopment of 1e Wormenseweg. Under the design, the road will be 6 metres wide and on-road parking will remain permitted, as is currently the case. To improve road safety, raised crossing platforms and several road narrowings will be introduced, featuring greenery and, where possible, trees. In addition, a green strip will be created on the odd-numbered side of the road between Oude Beekbergerweg and Ruys de Beerenbrouckstraat. Pavements will remain on both sides of the road and will have a minimum width of 1.50 metres.

Take a look at the four sketches of the preliminary design and find out what’s changing.

Sketch sheets 1, 2 and 3

This is a sketch of 1e Wormenseweg in Apeldoorn, showing what the street is intended to look like in future. It is a preliminary design and is spread over three sheets.

The drawing is a map viewed from above, based on an aerial photograph.

Here’s what’s going to change:

  • The road is being resurfaced with stones instead of tarmac. These stones make less noise.
  • The pavements are being resurfaced.
  • There are raised sections at the side streets. These are raised sections of road. The pavement simply continues there.
  • Special ramp sections will be installed in the pavement for people with disabilities.
  • New trees and green spaces are to be planted. It has not yet been decided which species will be planted.
  • A few lampposts are being moved.
  • Yellow lines will be painted in areas where cars are not allowed to park

Preliminary design, sheet 1 Preliminary design, sheet 2 Preliminary design, sheet 3

Sketch sheet 4

This is a drawing showing three cross-sections of the 1st Wormenseweg. A cross-section shows what the street looks like if you were to cut through it from the side. Below that are photographs of different tree species. It is a preliminary design.

Cross-section A-A’
This profile shows a typical section of road. The carriageway is 6 metres wide and has new, low-noise paving stones. On both sides there is a footpath made of grey paving slabs. The footpath on the left is 1.80 metres wide. The footpath on the right is 2.59 metres wide. In the drawing, a car and a cyclist are travelling on the carriageway.

Cross-section B-B’
This profile shows a section of road with a tree. The carriageway is 4 metres wide here. To the right of the carriageway is a green area with a tree. Next to this is a narrow footpath. The drawing shows a car on the carriageway.

Cross-section C-C’
This profile shows a section of street with a 6-metre-wide tarmac road. On the left is a driveway set into the pavement. On the right is a 2-metre-wide green strip and a 1.50-metre-wide footpath. In the drawing, a cyclist is riding on the road.

Tree species
Below are photos of seven tree species, showing their leaves and autumn colours:

  • small-leaved lime (two species)
  • Freeman maple (two varieties)
  • Soft ash, also known as American ash (two species)
  • Honey tree

Preliminary design cross-section

The residents’ evening was well attended and we can look back on a positive meeting. Many residents said they were satisfied with the revised design. We have incorporated as many comments and points for consideration as possible from previous consultation sessions. We will discuss the comments raised during the evening with the project team. Where possible, we will incorporate these into the further development of the design. As this is a preliminary design, no major changes are expected at this stage.

We will soon be publishing a response document on this page, setting out all the comments we have received and our replies to them.

Planning and follow-up

In the coming period

  • 5 October 2026

    presentation of the preliminary design

  • Autumn 2026

    process comments and publish a response

  • 2027

    further development towards the final design

As soon as we know more about the next steps, we will post that information on this page.

Residents’ Evening, 15 July 2025

Before we drew up a preliminary design, we asked local residents about the positive and negative aspects of the current situation. The central location of 1e Wormenseweg was cited as a major advantage. The variety of housing, the width of the street, the village-like character and the 30 km/h zone were also appreciated. The main areas for improvement related to road safety, traffic congestion, traffic speed, parking, the condition of the road and the lack of green spaces. The local council also saw opportunities to replace the tarmac and sewerage system, improve the traffic situation and add more green spaces.

Preliminary design and response document 2025

In 2025, the local authority drew up an initial preliminary design for the 1st Wormenseweg. This design was presented to local residents. The numerous responses to that design prompted the development of a new design; the responses to the comments made at the residents’ meeting on 15 July 2025 can be found in the Response Paper 2025.

More information

Do you have any questions about this work? Or would you like to find out more?
Get in touch

More projects in the South West